Proceedings of the ... International Conference on Offshore Mechanics and Arctic Engineering, Volume 1; Volume 7, Part 1American Society of Mechanical Engineers, 1988 - Arctic regions |
From inside the book
Results 1-3 of 81
Page 411
... components of the tree system which experience high wear rates or are necessarily complex ; both aspects may lead to failure during operation . The maintenance of these tree components can be achieved in one of two ways , either by ...
... components of the tree system which experience high wear rates or are necessarily complex ; both aspects may lead to failure during operation . The maintenance of these tree components can be achieved in one of two ways , either by ...
Page 412
... components of the tree requiring replacement or operation by the intervention system shall be identified . The control of the tree shall be from a production facility located between 3 and 5 km away using a multiplexed electro ...
... components of the tree requiring replacement or operation by the intervention system shall be identified . The control of the tree shall be from a production facility located between 3 and 5 km away using a multiplexed electro ...
Page 536
... components may be difficult to foresee . • with a bundle assembly ( fig . 2 ) , in which all the components lay parallel around a common axis , problems will arise in handling , mainly for storage on drums . For these reasons , winding ...
... components may be difficult to foresee . • with a bundle assembly ( fig . 2 ) , in which all the components lay parallel around a common axis , problems will arise in handling , mainly for storage on drums . For these reasons , winding ...
Contents
FLOATING PRODUCTION SYSTEMS | 1 |
OFFSHORE MECHANICS | 23 |
Early Production Systems in the North | 31 |
Copyright | |
37 other sections not shown
Other editions - View all
Common terms and phrases
analysis angle applied axial bending cable calculated characteristics coefficient components Conference connected considered construction cost curve damage depth determined diameter direction displacement distribution dynamic effect element energy Engineering equation equipment fatigue field Figure flexible flow forces frequency function geometry given important included increase installation International joint length limit linear load lower mass material matrix maximum mean measured Mechanics method mode mooring motion natural normal obtained Offshore operation parameters performance period pile pipe pipeline platform position presented pressure problem production range ratio response riser shear shown shows significant soil static stiffness strength stress structure surface Table Technology tension tower turbine vane vessel wave weight wire