[ocr errors][merged small][merged small]

1) A provision that the sale, use, or possession

of illegal drugs within the protected
area will result in immediate revocation
of access to vital areas and discharge
from nuclear power plant activities.
The use of alcohol or abuse of legal

- drugs within the protected area will
result in immediate revocation of access
to vital areas and possible discharge

from nuclear power plant activities.

2) A provision that any other sale, possession,
or use of illegal drugs will result in
immediate revocation of access to vital
areas, mandatory rehabilitation prior
to reinstatement of access, and possible

discharge from nuclear power plant activities.

3) Effective monitoring and testing procedures
to provide reasonable assurance that
nuclear power plant personnel with access

[merged small][ocr errors]
[ocr errors]

The industry, by periodic briefings or other appropriate methods, is expected to keep the Commission informed on program status. The NRC may also from time to time ask individual licensees to provide such information as the Commission may

need to assess program adequacy. ENFORCEMENT

Violations of any applicable reporting requirement or instances of a person being unfit for duty such that plant safety ipotentially affected will be subject to the enforcement process. Any NRC staff enforcement action pertaining to fitness for duty during this grace period will be undertaken only with

Commission concurrence.

In addition to required reports and inspections, information requests under 10 CFR 50.54(f) may be made and enforcement meetings held to ensure understanding of corrective actions. Orders may be issued where necessary to achieve corrective

actions on matters affecting plant safety.

In brief, the NRC's decision to use discretion in enforcement in order to recognize industry initiatives in no way changes the NRC's ability to issue orders, call enforcement meetings, or suspend licensees should a significant safety problem

be found.

Nothing in this Policy Statement shall limit the authority of the NRC to conduct inspections as deemed necessary to take appropriate enforcement action when regulatory requirements ENCLOSURE NO. 2

are not met.

NUCLEAR REGULATORY COMMISSION

COMMISSION POLICY STATEMENT ON
FITNESS FOR DUTY OF NUCLEAR POWER PLANT PERSONNEL

AGENCY: Nuclear Regulatory Commission ACTION: Final Commission Policy Statement on Fitness for Duty of Nuclear Power Plant Personnel SUMMARY: This statement presents the policy of the Nuclear Regulatory Commission (NRC) with respect to fitness for duty and describes the activities that the NRC will use to execute its responsibilities to ensure the health and safety of the public. To provide reasonable assurance that all nuclear power plant personnel werking-in WITH ACCESS T0 vital areas at operating plants are fit for duty, licensees and applicants wikł ARE develop|NG and implementing fitness for duty programs USING GUIDANCE in aeeeeeanee-with the Edison Electric Institute (EEI) "EEI Guide+ines to Effective Drug and Alcohol/Fitness for Duty Policy Development." she-guide+ines-wiłł-be-previeed-te-the-NRG-fer review-and-eemento It remains the continuing responsibility of the NRC to independently evaluate applicant development and licensee implementation of fitness for duty programs to ensure that desired results are achieved. Nothing in this Policy Statement limits NRC's authority or responsibility to follow up on operational events or its enforcement authority when regulatory requirements are not met. However, while evaluating the effectiveness of this guidance, the NRC intends to exercise discretion in enforcement matters related to fitness for duty programs for nuclear power plant personnel and refrain from new rulemaking in this area for a period of at least eighteen months from the

effective date of this Policy Statement.

EFFECTIVE DATE: (upon publication in the Federal Register)

FOR FURTHER INFORMATION CONTACT: Lcren Bush, Operating Reactor Programs
Branch, Office of Inspection and Enforcement, U.S. Nuclear Regulatory

Commission, Washington, D.C. 20555, telephone (301) 492-8080.
SUPPLEMENTARY INFORMATION:
BACKGROUND

The Nuclear Regulatory Commission (NRC) recognizes drug and alcohol abuse problems to be a social, medical, and safety problem affecting every segment of our society. Given the pervasiveness of the problem it must be recognized that it exists to some extent in the nuclear industry. Prudence, therefore, requires that the Commission consider additional appropriate measures to provide reasonable assurance that a person who is under the influence of alcohol or any substance legal or illegal which affects his ability to perform his duties safely, is not allowed access to a vital area at a nuclear power

plant.

The nuclear power industry, threugh WITH ASSISTANCE FROM programs developed and coordinated by EEI and the Institute of Nuclear Power Operations (INP0),

has made and is continuing to make substantial progress in this area.

A Task Force on Drug Abuse Problems, Policies, and Programs established IN

1982 by EEI's Industrial Relations DIVISION Executive Advisory Committee,