Roofing assemblies, roof coverings and roof structures shall be as specified in
this code and as otherwise required by this chapter. Subject to the requirements
of this chapter, combustible roofing and roof insulation may be used in any type
of ...
Roofing assemblies, roof coverings and roof structures shall be as specified in
this code and as otherwise required by this chapter. Subject to the requirements
of this chapter, combustible roofing and roof insulation may be used in any type
of ...
Page 1-146
THERMOPLASTIC MEMBRANE ROOF COVERING is a sheet membrane
composed of polymers and other proprietary ingredients, in compliance with UBC
Standard 15-6, whose chemical composition allows the sheet to be welded
together ...
THERMOPLASTIC MEMBRANE ROOF COVERING is a sheet membrane
composed of polymers and other proprietary ingredients, in compliance with UBC
Standard 15-6, whose chemical composition allows the sheet to be welded
together ...
Page 1-335
Roofing materials and methods of application shall comply with the UBC
standards or shall follow manufacturer's installation requirements when approved
by the building official. SECTION 1515 — INSPECTION AND WRITTEN
APPROVAL ...
Roofing materials and methods of application shall comply with the UBC
standards or shall follow manufacturer's installation requirements when approved
by the building official. SECTION 1515 — INSPECTION AND WRITTEN
APPROVAL ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Other editions - View all
Common terms and phrases
accessible accordance with Section aggregate aisle applied approved area of refuge ASTM automatic sprinkler system B.W. gage braced wall lines building official building or structure ceiling cement combustible comply compressive strength concrete conform corridor Division 3 Occupancies doors dwelling units elevator equipment exceed EXCEPTION exit-access exterior walls fire assembly Fire Code fire-resistive construction fire-resistive rating floor area grade Group H grout gypsum hazardous height inches inspection installed insulation joists live load located masonry materials maximum means of egress minimum N/C less nails noncombustible occupancy separation occupant load one-hour fire-resistive openings panels percent perlite portion portland cement reinforcement requirements of Section roof rooms Select Structural sheathing slope smoke smoke detector space specified in Chapter specified in Section square feet stairways standpipes steel storage story studs surface Table thickness tion Type UBC Standard units vertical veneer ventilation vermiculite vertical in 12 water closet width wire wood