Uniform Building Code, Volume 3International Conference of Building Officials, 1994 - Building laws |
From inside the book
Results 1-3 of 69
Page 3-16
... LOADING Throughout the fire - endurance and fire and hose stream tests , apply a constant superimposed load to simulate a maximum load condition . The applied load shall be as nearly as practicable the maximum load allowed by design ...
... LOADING Throughout the fire - endurance and fire and hose stream tests , apply a constant superimposed load to simulate a maximum load condition . The applied load shall be as nearly as practicable the maximum load allowed by design ...
Page 3-123
... load to allowable load is equal to or less than 50 , Z = 1.5 . Where the ratio of applied load to allowable load is greater than 50 , Z shall be determined in accordance with the following formula . Z = 0.9 + 30 / r , where r = ratio of ...
... load to allowable load is equal to or less than 50 , Z = 1.5 . Where the ratio of applied load to allowable load is greater than 50 , Z shall be determined in accordance with the following formula . Z = 0.9 + 30 / r , where r = ratio of ...
Page 3-512
... load of four times the de- sign load when installed in the manner intended for use . Test loads shall be applied for a period of one hour . 10.304.2 Exit ladder devices of the retractable type shall , in addition to the static load ...
... load of four times the de- sign load when installed in the manner intended for use . Test loads shall be applied for a period of one hour . 10.304.2 Exit ladder devices of the retractable type shall , in addition to the static load ...
Contents
General Building Limitations | 3-1 |
Administrative Fire and LifeSafety and Field Inspection Provisions | 3-3 |
Chapter | 3-9 |
Copyright | |
102 other sections not shown
Other editions - View all
Common terms and phrases
accordance ANSI applied approved assembly ASTM authority having jurisdiction beams braces branch lines brick building official ceiling cement check valve classification combustible concrete masonry construction control valve curtain deck deflectors determined devices diameter dimensions distance door drain dry pipe valve duct edge equipment exceed Exception feet fire department connection fire test fire-resistance rating flange floor flow furnace grade gypsum hangers Hazard Occupancies heat horizontal hydrostatic test installed joints joist klers knot length less limited liquid limit listed load located material maximum minimum mortar nails NFPA noncombustible Obstruction opening operation percent permitted pipe system portland cement preaction pressure protection riser roof Screw SECTION side spaced specified sprinkler system sq ft standpipe system storage structural steel structural steel columns Table temperature test sample thermocouples tion tube Type U.B.C. Standard Uniform Building Code units vertical wall thickness water supply welding width wood