... addition , fewer and fewer operators want to own capital equipment like a C / WO System which must be constantly operated , maintained and stored . Recognizing this , in early 1993 Sonsub bid on and was awarded a contract by Shell ...
... addition , fewer and fewer operators want to own capital equipment like a C / WO System which must be constantly operated , maintained and stored . Recognizing this , in early 1993 Sonsub bid on and was awarded a contract by Shell ...
Page 9
... addition to the two remote panels , a shutdown may be initiated at the MCU or the UCU and provisions for an externally supplied shutdown signal have been included at the MCU . During the flow testing of the Popeye wells , two remote ESD ...
... addition to the two remote panels , a shutdown may be initiated at the MCU or the UCU and provisions for an externally supplied shutdown signal have been included at the MCU . During the flow testing of the Popeye wells , two remote ESD ...
Page 10
... addition of the multiplex unit and accumulator package . The EDP / SCU shipping skid / test stump will also be expanded to include testing functions required for the multiplex unit . The number and styles of the riser clamps will ...
... addition of the multiplex unit and accumulator package . The EDP / SCU shipping skid / test stump will also be expanded to include testing functions required for the multiplex unit . The number and styles of the riser clamps will ...
Contents
Operational | 1 |
Technological Problems Associated With Subsea Development of High Pressure | 17 |
New Concept for a General Purpose Subsea Installation System | 23 |
Copyright | |
10 other sections not shown
Other editions - View all
Common terms and phrases
Agip alignment ball valves boosting unit bore buoy buoyancy cable chain clamps completion configuration connection control force Control System cost crane vessel deep water deepwater deployed deployment line DFCS DIVERLESS downhole drilling end effector equipment feedback field Figure flowline flowline connector fluid Gulf of Mexico heave compensated horizontal Hurricane Opal hydrate hydraulic inspection integration interface jumper LAPV loads located lube oil measurement meters modules motion Motion Compensation multiphase boosting multiphase flow objective trajectory offshore operation package performed phase pipe pipeline Popeye Popeye installation position pressure pull-in pump realized trajectory retrieval Riser and Control riser joint RUNNING TOOL SAF system Scene Reconstruction simulation skid Snamprogetti Sonsub spool Statoil subsea production system subsea structure subsea tree Surface Tree tasks TElerobotic thrusters tie-in tubing hanger tunnel umbilical underwater valves vehicle vessel water depth wellhead winch wireline WOCS