Page 7
... equipment to be installed , especially when swaying during storm force winds and seas . After the first tubing hanger installation , a new wider lift plate ( proof - tested to 1.5 million lbs . tension ) was installed while on the rig ...
... equipment to be installed , especially when swaying during storm force winds and seas . After the first tubing hanger installation , a new wider lift plate ( proof - tested to 1.5 million lbs . tension ) was installed while on the rig ...
Page 9
... equipment . An alarm sounded at any level of shutdown at the MCU and at Schlumberger's manifold control panel . The operation of all ESD equipment was thoroughly tested prior to flaring operations and several fire drills were held using ...
... equipment . An alarm sounded at any level of shutdown at the MCU and at Schlumberger's manifold control panel . The operation of all ESD equipment was thoroughly tested prior to flaring operations and several fire drills were held using ...
Page 10
... equipment have been defined and are briefly described in the following paragraphs . A thorough analysis of the ... Equipment . Obviously , it was necessary to increase the number of riser joints for the water depth . The existing riser ...
... equipment have been defined and are briefly described in the following paragraphs . A thorough analysis of the ... Equipment . Obviously , it was necessary to increase the number of riser joints for the water depth . The existing riser ...
Contents
Operational | 1 |
Technological Problems Associated With Subsea Development of High Pressure | 17 |
New Concept for a General Purpose Subsea Installation System | 23 |
Copyright | |
10 other sections not shown
Other editions - View all
Common terms and phrases
Agip alignment ball valves boosting unit bore buoy buoyancy cable chain clamps completion configuration connection control force Control System cost crane vessel deep water deepwater deployed deployment line DFCS DIVERLESS downhole drilling end effector equipment feedback field Figure flowline flowline connector fluid Gulf of Mexico heave compensated horizontal Hurricane Opal hydrate hydraulic inspection integration interface jumper LAPV loads located lube oil measurement meters modules motion Motion Compensation multiphase boosting multiphase flow objective trajectory offshore operation package performed phase pipe pipeline Popeye Popeye installation position pressure pull-in pump realized trajectory retrieval Riser and Control riser joint RUNNING TOOL SAF system Scene Reconstruction simulation skid Snamprogetti Sonsub spool Statoil subsea production system subsea structure subsea tree Surface Tree tasks TElerobotic thrusters tie-in tubing hanger tunnel umbilical underwater valves vehicle vessel water depth wellhead winch wireline WOCS