The WOCS equipment controls the operation of the CRS equipment during all operating modes and is also used to control various other utility tools when running flowline jumpers , well jumpers , tree caps , etc.
The WOCS equipment controls the operation of the CRS equipment during all operating modes and is also used to control various other utility tools when running flowline jumpers , well jumpers , tree caps , etc.
Page 108
High stresses in these jumpers are usually seen at mid - span and at the elbows . If the jumper has a pigging requirement , internal diameters may have to be kept consistent with the pipeline / manifold piping . Connector capabilities .
High stresses in these jumpers are usually seen at mid - span and at the elbows . If the jumper has a pigging requirement , internal diameters may have to be kept consistent with the pipeline / manifold piping . Connector capabilities .
Page 110
The distances and relative orientations between the subsea structures to be connected by the jumpers can be determined with the aid of measurement tools within a certain degree of accuracy . The jumper must be designed to be flexible ...
The distances and relative orientations between the subsea structures to be connected by the jumpers can be determined with the aid of measurement tools within a certain degree of accuracy . The jumper must be designed to be flexible ...
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Operational | 1 |
Technological Problems Associated With Subsea Development of High Pressure | 17 |
Gianfederico Citi Stuart Cowen and Alessandro Radicioni | 23 |
Copyright | |
10 other sections not shown
Other editions - View all
Common terms and phrases
addition alignment allow applications boosting bore buoyancy cable carried clamps completion configuration connection connector considered construction cost deep deepwater deployed deployment DFCS disturbance drilling effective Engineers equipment experience field Figure flow flowline fluid force function hydraulic improved increase inspection installation integration Italy Joint jumper learning length limited loads located lower maintenance manipulator means measurement mechanical method Mode motion multiphase objective offshore operation package performed phase pipe pipeline Popeye position possible present pressure problems production production system pump reference relative reliability response retrieval riser seal simulation Sonsub Spanner Joint spool structure subsea surface tasks tie-in tool trajectory Tree tubing hanger tunnel umbilical unit valves vehicle vertical vessel water depth weight winch