Proceedings of the ... International Conference on Offshore Mechanics and Arctic Engineering, Volume 15, Part 6American Society of Mechanical Engineers, 1996 - Arctic regions |
From inside the book
Results 1-3 of 9
Page 45
1996 OMAE — Volume VI , Subsea Technology ASME 1996 TROLL PHASE I , LANDFALL TUNNEL INSPECTION BY USE OF VIRTUAL REALITY TECHNOLOGY Svein E. Skjei Johann H. Kuhlmann A / S Norske Shell PB 60 5049 Sandsli - Bergen Norway tel : ( 47 ) 55 ...
1996 OMAE — Volume VI , Subsea Technology ASME 1996 TROLL PHASE I , LANDFALL TUNNEL INSPECTION BY USE OF VIRTUAL REALITY TECHNOLOGY Svein E. Skjei Johann H. Kuhlmann A / S Norske Shell PB 60 5049 Sandsli - Bergen Norway tel : ( 47 ) 55 ...
Page 46
Based on the study results , it was concluded that tunnel intervention is viable by means of a free swimming ROV connected to a purpose built umbilical system . The following alternatives were considered . Utilisation of a battery ...
Based on the study results , it was concluded that tunnel intervention is viable by means of a free swimming ROV connected to a purpose built umbilical system . The following alternatives were considered . Utilisation of a battery ...
Page 47
Also , the locations of the features were clearly marked on the three dimentional model of the tunnels so that an ... TUNNEL INSPECTIONREPORTING SYSTEM There are four main elements to the Troll Tunnel inspection and reporting systems .
Also , the locations of the features were clearly marked on the three dimentional model of the tunnels so that an ... TUNNEL INSPECTIONREPORTING SYSTEM There are four main elements to the Troll Tunnel inspection and reporting systems .
What people are saying - Write a review
We haven't found any reviews in the usual places.
Contents
Operational | 1 |
Technological Problems Associated With Subsea Development of High Pressure | 17 |
Gianfederico Citi Stuart Cowen and Alessandro Radicioni | 23 |
Copyright | |
10 other sections not shown
Other editions - View all
Common terms and phrases
addition alignment allow applications boosting bore buoyancy cable carried clamps completion configuration connection connector considered construction cost deep deepwater deployed deployment DFCS disturbance drilling effective Engineers equipment experience field Figure flow flowline fluid force function hydraulic improved increase inspection installation integration Italy Joint jumper learning length limited loads located lower maintenance manipulator means measurement mechanical method Mode motion multiphase objective offshore operation package performed phase pipe pipeline Popeye position possible present pressure problems production production system pump reference relative reliability response retrieval riser seal simulation Sonsub Spanner Joint spool structure subsea surface tasks tie-in tool trajectory Tree tubing hanger tunnel umbilical unit valves vehicle vertical vessel water depth weight winch